Case Study: Fuller Normal Advanced Technology Charter School, Greensville, South Carolina

 

Buildings Available for Immediate Delivery
 

Download a PDF  - Request a Quote

Permanent Modular Education Building – Over 10,000 Square Feet

Building Size:  218' x 66'
Total Square Footage: 14,385

The Client:
The Fuller Normal Advanced Technology Charter School offers students a unique, innovative, and technologically enriched educational opportunity for K-5students on a 75 acre campus with state-of-the-art facilities. Class size is limited to 20 students in a class and the instruction is highly individualized from a staff dedicated to student achievement.

The Need:
The Fuller Nwmal Advanced Technology School was in need of a complete school complex that could be in place and functional on a very tight time-table. Due to the need to have a building in place within a few months, conventional construction would not get this project done on time. Modular construction was the solution determined but with a design constraint that the building must mirror the look of the surrounding brick buildings

The Solution:
Designed as a complete stand alone modular school with a 'full school setting', the project brought the school and the community together to create a modular classroom complex that would integrate visually and operationally with its surrounding. The exterior brick fac;ade was created to compliment the adjacent brick buildings. The HVAC system was designed with units located in the rear of the building and screened by the greenbelt. The interior layout was created to provide the most classrooms with the available space. The building houses 13 classrooms, 3 administrative offices, 1 nurse station, 2 faculty bathrooms, and 2 boys and girls multi-stall bathrooms.

The Result:
Production of the building started on May 8,2006 and the building was fully occupied by August 14, 1006. With a total of 14,385 square feet, the 21 8'x66' building was designed to be at ground level so that it eliminated the need for any steps or ramps. The perimeter foundation also incorporated a brick shelf to support the fa~ade. A special roof was designed to slope from one end of the building to the other with an integrated gutter system would not be visible. The zoned HVAC system included programmable thermostats in each classroom and throughout the offices and administrative areas for energy efficiency. The cost effectiveness of the modular construction and the speed in which the facility could be completed> was the deciding factor in the selection of M Space as the company most capable of providing the needed modular solution.

Testimonial:
"I worked clirectly with M Space in developing the modular plans for our Charter School. The M Space building was designed to handle 250 students. The plan worked superbly well and I was supremely satisfied with everything that was done. M Space was right there with us every step of the way." Dr. David Church